You will need to a obtain a demolition permit if you are planning to demolish a building or part of a building:
If you want to demolish a building or part of a building that does not require a building permit, normally you also do not need a demolition permit either, unless the municipality has decided otherwise.
You must submit an application for a demolition permit even if only a small part of the building is to be demolished.
Explain the fees structure which is required for obtaining the certificate/document.
Explain the time until which the certificate/document is valid. e.g. Birth Certificate Valid Forever
Please attach documents that can be used by people. e.g. links
Please attach sample completed documents that would help other people.
Please explain processing time taken in obtaining the document/certificate.
Videos explaining the procedure or to fill the applications. Attach videos using the following tag <&video type="website">video ID|width|height<&/video&> from external websites. Please remove the "&" inside the tags during implementation. Website = allocine, blip, dailymotion, facebook, gametrailers, googlevideo, html5, metacafe, myspace, revver, sevenload, viddler, vimeo, youku, youtube width = 560, height = 340, Video ID = Can be obtained from the URL of webpage where the video is displayed. e.g In the following url "http://www.youtube.com/watch?v=Y0US7oR_t3M" Video ID is "Y0US7oR_t3M".
Application to obtain a demolition permit or notifications of demolition must be submitted to the local municipality.
The municipality is also the supervisory authority.
A list which displays the kind of information which is required to complete the procedure. e.g. 1. Date of Birth. 2. City or County of Birth.
This procedure provides information on how you can obtain a Demolition Permit in Sweden.
Notification of demolition
There are cases where you do not need a demolition permit, but you may still need to submit a notification of demolition.
This applies when you want to demolish a building or part of a building that lies outside the area covered by the municipality's local plan. To demolish ancillary buildings to detached or semi-detached houses, you do not need to submit a notification.
If your demolition permit is granted or you have submitted a notification of demolition, you must await the go-ahead notification from the building committee before you can start demolishing the building.
Requirements
The demolisher must conduct checks and testing to the extent required by Sweden's Plan- och bygglag (2010:900) (Planning and Building Act). The demolition must be performed in accordance with the plan and observe due care.
For almost all demolition projects, there must be an inspection manager who is independent in relation to the demolisher. The inspection manager is to assist the developer in drawing up a plan for checking the demolition. An application for a demolition permit or notification of demolition is to state the name of the inspection manager.
Please explain what are other uses of obtaining this document/certificate. e.g. Birth Certificate can be used as proof of identity.
More information which might help people.