Philippines - Apply for Clearance to Undertake System Impact Study (SIS)
ProcedureEdit
Online Appointment:
- The applicant has to make an appointment before vising the office using the following link
- The applicant has to enter the following details to make an appointment:
- Email Address
- Name
- Office, Company, Affiliation or Organization Name
- Company / Business Address
- Contact Number
- Office to visit
- Person to visit or transact with
- Nature or purpose of visit
- Date of visit
- Time of visit
- Other details on the appointment
- After entering all the above-mentioned details, the applicant will receive and appointment schedule via email.
- On the appointed date the applicant has to visit the office.
Apply In-Person:
- To Apply for Clearance to Undertake a System Impact Study (SIS), the applicant has to approach the Philippines Department of Energy nearby offices link
- The applicant has to write a request letter to the concerned officer as advised.
- Make sure that the applicant has attached all the necessary documents that are mentioned in the “Required Documents” section of this page.
- The applicant has to attach the photocopies of the required documents along with the application form while submitting.
- Submit all the documents with the completed form to the concerned officer.
- The applicant has to pay the prescribed fee as requested by the authority.
- After receiving the application, the concerned authority will check the submitted application and document set. If all are in place, the application will be accepted.
- All applications are processed within a reasonable time, having regard to the particular circumstances of each application, including the completeness of information and documents submitted to the authority by the applicant.
- The authority may seek additional information from an applicant if this is necessary to assess the application. The authority does not need to deal further with an application until the applicant has provided this additional information.
- Once everything is accepted the Authority will provide the certificate.
- This entire process can be completed within 10 days or as per the timeline advised by the respective department authority.
Required DocumentsEdit
- Letter of Request
- Company Profile
- Project Background
- Additional for RE Projects
- Endorsement from REMB
- Copy of Service Contract
Office Locations & ContactsEdit
DEPARTMENT OF ENERGY – PHILIPPINES
Main Office
Energy Center, 34th St., Rizal Drive,
Bonifacio Global City, Taguig City,
Philippines 1632
Trunkline Number: (632) 8479-2900
Email Address: [email protected]
Luzon Field Office
Government Center, Nueva Vizcaya, P
angasinan Road, Brgy. Carmay East (Purok 06) Rosales 2441,
Pangasinan
Telephone Number:(075) 653-0233, (02) 8479-2900 local 570/572
Telefax: (075) 656-0114
Email address: [email protected] , [email protected]
Visayas Field Office
3rd Floor, Escario Building,
731 Escario Street, Capitol Site, Cebu City
Telephone Nos: (032) 253-2150; 253-7222; 253-3459
Email Address: [email protected]
Mindanao Field Office
3rd Floor, Tolentino 2020 Building, A. Candelaria Street,
Ecoland Drive, Matina, Davao City
Mobile Nos.:
Globe - 0906 1844428
Smart - 0909 8943328
Email Address: [email protected]
Contact Details link
EligibilityEdit
- Any Generation Companies conducting feasibility study/due diligence in preparation for their generation power project who intend to Apply for Clearance to Undertake a System Impact Study (SIS) is eligible to make this application.
FeesEdit
- The applicant has to pay the prescribed fee as requested by the authority officer.
- Use the following link to know more about fees and Charges link
ValidityEdit
Explain the time until which the certificate/document is valid. e.g. Birth Certificate Valid Forever
Documents to UseEdit
Please attach documents that can be used by people. e.g. links
Sample DocumentsEdit
Please attach sample completed documents that would help other people.
Processing TimeEdit
- This entire process can be completed within 10 days or as per the timeline advised by the respective department authority.
Related VideosEdit
Videos explaining the procedure or to fill the applications. Attach videos using the following tag <&video type='website'>video ID|width|height<&/video&> from external websites. Please remove the '&' inside the tags during implementation. Website = allocine, blip, dailymotion, facebook, gametrailers, googlevideo, html5, metacafe, myspace, revver, sevenload, viddler, vimeo, youku, youtube width = 560, height = 340, Video ID = Can be obtained from the URL of webpage where the video is displayed. e.g In the following url 'http://www.youtube.com/watch?v=Y0US7oR_t3M' Video ID is 'Y0US7oR_t3M'.
InstructionsEdit
- Applicants must complete the application form before submitting it. Incomplete applications will not be accepted.
- Applicants must provide genuine information while applying for this procedure.
Required InformationEdit
- Name of the applicant
- Address
- Telephone number
- Fax no
- TIN no
- Business details
- Project details
- Investment details
Need for the DocumentEdit
- Clearance to Undertake System Impact Study (SIS) refers to the approval granted by an organization or regulatory body to an entity or project developer to conduct a comprehensive study of the potential impact of the proposed project on the power system.
Information which might helpEdit
- For more information link
Other uses of the Document/CertificateEdit
Please explain what are other uses of obtaining this document/certificate. e.g. Birth Certificate can be used as proof of identity.
External LinksEdit
OthersEdit
- The System Impact Study is a critical component of the interconnection process for generators, transmission facilities, and other power system equipment. The study examines the potential impact of the proposed project on the reliability, stability, and safety of the power system.