Step 1 : First one has to make sure that all the required documents are in hand to apply online. If you would like to know about the documents that are required for this procedure, please visit the following link : Required Documents for Obtaining Electricity Connection
Step 2 : Please use the following link to apply online : Apply Online.
Step 3 : Please complete the application form with valid details.

File:Nagaland electric 1.gif

Step 4 : After completion please click “Validate” tab which is highlighted in RED in the below image.

File:Nagaland electric 2.gif

Step 5 : The outcome of the above process can lead user to apply for connection by following the rest of the page requirements.
Step 6 : Please save the online generated acknowledgement receipt for future reference.
Step 7 : This submitted application will be processed further. Notification from department (through SMS or over phone) for further process will reach applicant.
Step 8 : Applicant shall go to the respective office with the printout of application along with other documents and follow the guidelines to get the connection.