ProcedureEdit

How to Apply
In-Person

  1. You should visit the Électricité de Djibouti (EDD) branch office near you approach the service desk and express your interest.
  2. Fill out the application form, attach the supporting documents (listed below) and submit to the attending officer for verification and processing.
  3. After your application is approved, EDD will have some of its personnel visit your residence to verify the compliance of standards within 3 to 7 days. The officers will also estimate the amount you will be required to pay for the connection.
  4. Depending on the quoted costs, you will be required to proceed with payments at the EDD office, where you will be issued with a receipt.
  5. Upon payment of the required cost, External works, meter installation, and other essential processes will be done to make sure you can access electricity in 5 working days.

Online Application

  1. You should visit the Link or download the EDD app to make the application.
  2. Click on the “connection request online request form’ on the right hand side of the page.
  3. You will be redirected to the next page, Fill in the all the required field accurately then click on Following.
  4. You will then be redirected to the 2nd page, fill in the required field accurately then click on Next.
  5. You will then redirected to the 3nd page, fill in the required field accurately and verify that all the information are in order if satisfied then click on Competed.
  6. Your application will be sent to EDD for action. You will receive a notification of your application via email address and details about EDD site visit.
  7. EDD will have some of its personnel visit your residence to verify the compliance of standards within 3 to 7 days. The officers will also estimate the amount you will be required to pay for the connection.
  8. You will be required to visit the EDD office near you with the supporting documents and the quoted cost and make payment, where you will be issued with a receipt.
  9. Upon payment of the required cost, External works, meter installation, and other essential processes will be done to make sure you can access electricity in 5 working days.

Note : The client/applicant has 6 months to pay the quotation otherwise it expires and must reapply for a new connection again.

Advertisement

Required DocumentsEdit

  • Identification document(valid passport or ID card)
  • Title deed copy /Land Board Certificate / Lease Agreement
  • Route sketch leading to where supply is needed.
  • Quotation fee
  • Consent from the property owner
  • Any other documents that may be requested by the EDD official

Office Locations & ContactsEdit

Électricité de Djibouti Headquarters (EDD)
Address: Blvd de la Republique, Djibouti
Telephone: +253 21355368
Branches Contract:Link
Website: Link

EligibilityEdit

  • The service is open to all

FeesEdit

  • You will be given a quotation of the connection fees

ValidityEdit

  • Validity of the connection is forever, unless one fail’s to pay the electricity bill which lead to disconnection of the electricity service.

Documents to UseEdit

(electricity rate (traffic)

Sample DocumentsEdit

Please attach sample completed documents that would help other people.

Processing TimeEdit

  • Within 2 weeks upon payment of the required quotation cost.

Related VideosEdit

Videos explaining the procedure or to fill the applications. 
Attach videos using the following tag <&video type='website'>video ID|width|height<&/video&> from external websites. 	
Please remove the '&' inside the tags during implementation.
Website = allocine, blip, dailymotion, facebook, gametrailers, googlevideo, html5, metacafe, myspace, revver, 
sevenload, viddler, vimeo, youku, youtube
width = 560, height = 340, Video ID = Can be obtained from the URL of webpage where the video is displayed.
e.g In the following url 'http://www.youtube.com/watch?v=Y0US7oR_t3M' Video ID is 'Y0US7oR_t3M'.

InstructionsEdit

Please provide other instructions related to the certificate/documents.
e.g. The state office holds birth records since january 1908.

Required InformationEdit

  • Name of the applicant/company
  • Contact details of the applicant/company
  • Supply address (district, location, street, house name, and landmark)
  • ID card/passport number
  • Details of the residence (No. of rooms, No. of air conditioners, lighting points (bulbs) etc.)

Need for the DocumentEdit

  • All electricity connection in Djibouti are done by the Électricité de Djibouti (EDD).

Information which might helpEdit

Enter other informations which might help.

Other uses of the Document/CertificateEdit

Please explain what are other uses of obtaining this document/certificate.
e.g. Birth Certificate can be used as proof of identity.

External LinksEdit

(EDD)

OthersEdit

More information which might help people.