Assam - Apply for Agriculture Electricity Connection
Advertisement
ProcedureEdit
APPLY IN-PERSON:
- To apply for agriculture electricity connection in person visit ELECTRICITY BOARD OFFICE in your respective area
- The address and contact details of the office can be found in ‘’Office and Contact Details” section of this page
- Visit the Office and get the Application form for Agricultural Electricity Connection from the relevant department or you can download the application form from the following link: Link
- Please fill the application with essential information and details and it should be attested with the applicant along with all the partner’s signature
- Make sure that you have all the documents that are listed in “Required Documents” section of this page. Attach all the important documents mentioned
- Then, it should be submitted to the relevant authority. Also pay the required fees for the application process at the office as directed by the officials or you can find the required fee in “Fee Details” section of this page
- And your application and attached documents will be passed for verification to check if the land and area is eligible for the type of connection proposed
- After successful registration, an acknowledgement mentioning the registration number and date of registration will be given to the applicant
- Now, concerned officials will approve the application and orders will be issued.
Apply Online: - Apply for Agriculture Electricity Connection Online with Images
- To apply for agricultural electricity online, visit the following link: Link
- On the opened page click the ‘new connection’ category
- Now choose your applied category as 51- LT VII AGRICULTURE
- Enter the applied load in kw for the agriculture connection. To view allowed load of electricity visit the link- Link
- Now fill the consumer details correctly
- Provide the address of the Agricultural land for which the connection is to be made,
- Enter your Mobile number, PAN number, and aadhar number without error
- Now you will be seeing a 4 yes or no type questions, please read the questions and click on the correct option patiently
- Now upload your files not exceeding 100MB ,for Identity Proof, Residential address proof, Proof of the legal occupation of the premises, Test report from electrical contractor/ supervisor,and latest passport size photograph of the applicant (in jpeg/png format only) (OR) Refer “Required documents” section of this page
- Now give your declaration by clicking on the small square under declaration
- Once all the data’s are entered, Kindly check once and click on the Verify button
- If all your required fields are filled correctly, Submit button will be viable now. Click on the submit button.
- Now application warning will pop up on your screen, if you are confident enough on all the information provided, click on Submit or you can also review once and come back to submit the application
- Enter the OTP sent to your Mobile number
- Now make the payment as per the page prompt option and hit “pay now” to reach payment gateway page and complete payment.
- Once the payment is made, a transaction reference number will get generated. Keep it safe.
- With the transaction number user can obtain acknowledgement receipt.
- This submitted application will be processed further. Notification from department (through SMS or over phone) for further process will reach applicant
- Applicant shall go to the respective office with the printout of application along with other documents and follow the guidelines to get the connection.
Advertisement
Required DocumentsEdit
- Completed Application form
- Proof of ownership (Sale deed, katha, succession certificate, sanctioned plan from local authority.)
- Indemnity Bond as per format supplied by the electricity company, if you are not the owner of the premises
- No objection certificate (NOC) from the owner(If the applicant is tenant or lessee)
- Proof of permanent residential address (Ration card, PAN, telephone Bill, Insurance policy bond, voters identity card etc.)
- Clearances for establishment from the Pollution Control Board concerned where applicable residential / residential-cum-commercial premises of more than 100 flats)
- Self- certification for electrical installation of the premises of the consumer for which new connection is being applied for or the test results duly signed by the licensed Electrical Contractor
- Requisite Earnest Money as advised
- Proof of occupation or ownership of a premises through any one of the documents (Passport / Voter Identity Card / Rent Bill / Telephone Bill / Municipal or any other Tax Bill / Ration Card / Certificate from Panchayat)
- The detailed list of electrical equipment’s with number and corresponding wattages
- For LV & MV consumers, a sketch of new line required for service connection showing the premises from existing LV & MV line is required to be submitted by the intending consumer. (licensed electrical contractor will be helpful)
- NOC from local administration (assessment and collection department - no due & litigation free)
- NOC from respective department for digging (if applicable)
- Test Certificate of metering equipment, if consumer supplies the same.
- Land Paper
- Aadhar Card
- Photograph of the applicant
- Contact number
- Consents / Authorizations / Approvals wherever applicable.
- Service Connection Agreement, if applicable.
- Consent of the owner of the property if the proposed service line has to pass through the property of some other persons
Note:
- All original and copy of original with self attestation as advised by respective authorities to submit as per requirement.
- Apart from the above documents authorities may ask to submit additional information or documents. Please provide them for processing.
Office Locations & ContactsEdit
Assam Power Distribution Company Ltd - APDCL
4th Floor, BijuleeBhawan,
PaltanBazar,
Guwahati– 781001,
Assam - India
Phone No.: +91 0361-2313069/2313082/7140001
Fax: +91 0361-2739527
Email ID:[email protected]
Contact Link:Link
NOTE: Kindly contact the Chief Engineer/Operation and Maintenance Officer of your nearest electricity board. Contact details of the Officers can be obtained from the above website. Please select your district and respective area officer and proceed accordingly.
EligibilityEdit
- Any person who wishes to set up a new electricity connection in their agricultural land can apply.
- The shareholders of the land should possess a no objection certificate sworn before the Executive Engineer/Operation and Maintenance Office of the jurisdiction concerned.
- The certificate should be obtained after verification from the Village Administrative Officer.
FeesEdit
Please contact your nearest Electricity Board for fee details.
ValidityEdit
Explain the time until which the certificate/document is valid. e.g. Birth Certificate Valid Forever
Documents to UseEdit
- Download the application form from the following link: Link
Sample DocumentsEdit
Please attach sample completed documents that would help other people.
Processing TimeEdit
- A minimum of 3 working days to a maximum of 3 months may take for the new agricultural electricity connection. The processing time also depends on the type of connection proposed.
Related VideosEdit
Videos explaining the procedure or to fill the applications. Attach videos using the following tag <&video type='website'>video ID|width|height<&/video&> from external websites. Please remove the '&' inside the tags during implementation. Website = allocine, blip, dailymotion, facebook, gametrailers, googlevideo, html5, metacafe, myspace, revver, sevenload, viddler, vimeo, youku, youtube width = 560, height = 340, Video ID = Can be obtained from the URL of webpage where the video is displayed. e.gIn the following url 'http://www.youtube.com/watch?v=Y0US7oR_t3M' Video ID is 'Y0US7oR_t3M'.
InstructionsEdit
- Please do fill the application form with correct information and fill all the required columns.
- Do submit the application to the concerned authority with required documents attached.
- Kindly pay the required amount for the application process while submitting the application form at the office.
Required InformationEdit
- Name and address of the organisation
- Availability of the land
- Contact details and email address
- Recent photograph of the applicant
- “No Objection Certificate”(NOC) from the Government Project official
- Signature of the applicant and partners as well
- Sketch showing the location issued by V.A.O.
Need for the DocumentEdit
- Any person who wishes to get a new agricultural electricity connection inside the state of ASSAM must apply for the same to the respective authority. Government provides electricity connection to those who apply for a new connection. This document will guide you to obtain the agricultural electricity connection in all means.
Information which might helpEdit
Enter information which might help
Other uses of the Document/CertificateEdit
Please explain what are other uses of obtaining this document/certificate. e.g. Birth Certificate can be used as proof of identity.
External LinksEdit
Place some external links which might help.
OthersEdit
More information which might help people.