Jharkhand - Online Obtain Electricity Connection

Revision as of 05:28, 29 April 2025 by Wesley (talk | contribs) (Auto)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)


Step 1 : First one has to make sure that all the required documents are in hand to apply online. If you would like to know about the documents that are required for this procedure, please visit the following link : Required Documents for Obtaining Electricity Connection
Step 2 : Please use the following link to apply online : Apply Online.
Step 3 : In the given page, please select “Consumer Services” menu and choose “New Connection” sub option for list of options. Then select “New Connection (LT)” to reach next page. Refer the below image where the options are highlighted in RED.

File:Jhar electric 1.gif

Step 4 : Now click “New User” tab at the bottom of the page for registration. Refer the below image where it is highlighted in RED.

File:Jhar electric 2.gif

Step 5 : Now complete the registration form and click on the checkbox highlighted in RED. Then click “Register” tab which is highlighted in RED in the below image.

File:Jhar electric 3.gif

Step 6 : After successful registration process, click “Click here for login” option which is highlighted in RED in the below image.

File:Jhar electric 4.gif

Step 7 : Now enter your username and password in the textbox and click on the checkbox highlighted in RED. Then click “Login” tab which is highlighted in RED in the below image.

File:Jhar electric 5.gif

Step 8 : Now click “New Connection (LT)” option under “REQUEST” menu. Refer the below image where it is highlighted in RED.

File:Jhar electric 6.gif

Step 9 : Please complete the application form with proper details and click “Next” tab. Refer the below image where it is highlighted in RED.

File:Jhar electric 7.gif

Step 10 : Also complete supply related details and click “Next” tab. Refer the below image where it is highlighted in RED.

File:Jhar electric 8.gif

Step 11 : To attach the documents click “Choose File” tab which is highlighted in RED. Then click “Next” tab. Refer the below image where it is highlighted in RED.

File:Jhar electric 9.gif

Step 12 : Choose applicable option to obtain new connection. Then click on the checkbox highlighted in RED and click “Finish” tab which is highlighted in RED in the below image to submit your request.

File:Jhar electric 10.gif

Step 13 : This submitted application will be processed further. Notification from department (through SMS or over phone) for further process will reach applicant.
Step 14 : Applicant shall go to the respective office with the printout of application along with other documents and follow the guidelines to get the connection.